ESTW Neukieritzsch Complex conversion project under special conditions
A special large-scale project in the Leipzig region
Can only be implemented as a well-coordinated team
It's done! The biggest track closure ever to take place on a Hasselmann Group railroad construction project has been brought to a successful conclusion without any significant setbacks. The closure of the major construction site in Neukieritzsch lasted a full eight weeks. Everything had to be perfectly prepared before the start. During the shutdown period, everything had to fit perfectly, mesh together, hand in hand, cog in cog, simply everything!
It's done! The biggest track closure ever to take place on a Hasselmann Group railroad construction project has been brought to a successful conclusion without any significant setbacks. The closure of the major construction site in Neukieritzsch lasted a full eight weeks. Everything had to be perfectly prepared before the start. During the shutdown period, everything had to fit perfectly, mesh together, hand in hand, cog in cog, simply everything!
It's done! The biggest track closure ever to take place on a Hasselmann Group railroad construction project has been brought to a successful conclusion without any significant setbacks. The closure of the major construction site in Neukieritzsch lasted a full eight weeks. Everything had to be perfectly prepared before the start. During the shutdown period, everything had to fit perfectly, mesh together, hand in hand, cog in cog, simply everything!
EUR 21 million
The order volume shows the trust our customers place in the Hasselmann Group
3.5 years construction time
The project was carried out reliably and according to plan
8,000 meters of track
A major project with 8,000 meters of track, 105,000 meters of cable, 50,000 m² of ground improvement, 1 passenger underpass, 1 passenger overpass and 6 platforms
Strong together: bundled expertise of the Hasselmann Group